Farms: ABB hands over Germany’s DolWin1 offshore wind energy link
Productivity | Information | History | View | Quality
2186View
ABB has successfully commissioned and handed over the DolWin1 offshore wind grid connection to the Dutch-German transmission system operator TenneT. The 800-megawatt High Voltage Direct Current (HVDC) link connects offshore wind farms around 75 kilometers off the German coast with the country’s transmission grid. The DolWin1 grid connection can integrate 800 MW of offshore wind power, enough to supply around one million households with clean energy. For more information, see our press release at http://www.abb.com/cawp/seitp202/CDAC928069A87E64C1257E90002C90B0.aspx
I am studying power electronics in University in Japan . I have always wanted to build those huge awesome renewable energy power plants.
How can I take part in building or designing those power plant systems?
Is it called "plant engineering"? if I get the job in those area, can I work on it?
what can I do while I'm studying?